Sunday, 13 February 2022

LAUNCH DATE SET FOR 1 ST OF APRIL (12.00 HRS ISH)  2022

Wednesday Phil and Wally still working 3 or 4 days a week to make sure the launch date can be achieved.


Wally had to make wooden bearings of different sizes  to fit in each wheel as their centres were different sizes. These were then fitted to the cradle with wooden spacers either side of the wheel for smooth running.
The sections of the recycled wave machine were then positioned under the hull to form the new cradle and Wally continues its construction.




Wednesday Phil meanwhile ,removed the one and a quarter inch outlet valves from the cockpit drains and replaced them with two inch ones which will allow faster draining if needed.
The cockpit outflows  had to be redesigned for the new valves and in order for maximum drainage these were sunk below the floor level by adding packing underside .These were epoxied in to make watertight.

The final section of the keel band was brought by Jeremy and after " Wally welding"  was finally secured by Phil.




Wednesday Phil continues making two pin rails to secure ropes to and now he understand the forces involved , has secured them in the hull via long threaded bar through the main beams below and strengthened them with metal internal brackets.


Meanwhile Mirela from Youth With A Mission came to sand down and varnish the floor boards from within the cabin and Ludovic  hoovered out all the bilges which is a difficult and contorting procedure.